The Ratiboř 361 PV project is co-financed by the EU Emissions Trading Scheme through the Modernisation Fund. The subject of the project is the installation of a PV plant with an output of 14.85 kWp on building no. 361 in the municipality of Ratiboř.
Total eligible expenditure: 415 000 CZK
Contribution from the Modernisation Fund: CZK 311 250
Contribution of the applicant: CZK 103 750
Project implementation period: 09/2023 - 10/2023